Memorizing M & C Processes (excluding Integration Management Knowledge Area) Inputs and Outputs

To begin with, if I say, there are 47 inputs and 49 outputs to and from the 9 Monitoring and Controlling Processes (excluding Integration Management Knowledge Area), and you have to memorize them. You think I am mad. I might appear mad towards getting my PMP Certification, but there is a method to my madness. Read carefully below...

Do you agree that

  • The Monitoring and Controlling Processes for each Knowledge area (excluding Integration Management that is not discussed here and Human Resources Management which doesn't have a Monitoring and Controlling process) have similar purpose?
  • Each knowledge area (again  excluding Integration Management that is not discussed here and Human Resources Management which doesn't have a Monitoring and Controlling process) produces certain key project documents, other than their respective management plans, with respect to its own knowledge area? For example, Scope Management produces Requirements Management Plan, Requirements Traceability Matrix. Time Management produces Project Schedule. Quality Management produces Quality Metrics, Quality Checklists etc.
  • If you have agreed to both the questions above, then you understand that since these processes perform similar activities with respect to their own knowledge areas, there must be some common Inputs and Outputs for these processes. Isn't it?
Enough said, let us look at the I/O Diagram...

Observations on Inputs
  • Project Management Plan and Work Performance Data (WPD) is input to all the 9 Processes. Which means by remembering these two, you can remember a total of 18 inputs.
  • Organizational Process Assets (OPA) is input to Scope, Schedule, Cost and Quality Controlling Processes that start with the word "Control". To remember easily, the last three knowledge areas - Risk, Procurements and Stakeholder's Controlling processes doesn't have OPA as input. This will make you to remember another 5.
  • Requirements Management Plan and Requirements Traceability Matrix both are key Project documents that are produced by Scope Management Knowledge area, so they are input to both the Validate Scope and Control Scope processes.
  • Project Schedule, Schedule Data and Project Calenders (this comes from Procurement process as well) produced from Schedule Management Knowledge area are inputs to its respective Controlling process.
  • Like this, observe how the other key Project documents and how they go as inputs into their respective knowledge area controlling processes. For ex: Risk Register is input to Control Risks.
  • Use logic for the rest of the inputs other than common ones, and you should easily remember them.
Observations on Outputs
  • This is mind blowing... by remembering just 5 common outputs, you can actually easily remember 40 outputs of the 49. Now you should appreciate my method to madness. And remembering these common 5 outputs, you can remember 5 knowledge areas completely. 
  • Change Requests, Work Performance Information (WPI), Project Document Updates, Project Management Plan Updates and Organizational Process Assets Updates - are the five common outputs from all the processes that start with the word "Control". 
  • Both Control Schedule and Control Costs processes produce their respective Forecasts. - Important to remember for the exam.
  • Check the rest of the outputs for Control Quality and Validate Scope.
For more information
  • How the deliverable is created, validated, verified and accepted, please check my another post Deliverable Lifecycle. Its important to see this post, as Validate Scope, Control Quality both have connections with respect to Inputs and Outputs above and you can clearly visualize them in that post.
  • How Work performance data (WPD), and Work performance information (WPI) and finally Work performance reports (WPR) is related, check my another blog Work Performance data to reports process flow
  • If you observe, you will note that all the Controlling processes produce Change Requests as outputs. If you would like to know the complete Change Management flow, please follow my Change Management Process Flow
Disclaimer
  • The abbreviations WPD, WPI and WPR I have used to reduce my typing work. They are not PMI(R) abbreviations.
  • I have used this method to memorize the inputs and outputs for Controlling processes. I am sharing this information here, with the assumption that it might be beneficial for others who are preparing for PMP Exam. If you find this post or any other post, not to your understanding please feel free to post a comment, I would be glad to explain more. If you find this information is not helpful for you, please don't mind, and I am thankful for your visit anyway.