Memorizing Project Cost Management Planning Processes Inputs and Outputs using Cascading Inputs Method

Project Cost Management is a very important knowledge area. As a Project Manager, your project's performance is constantly measured against cost (and other constraints such as Scope, Schedule etc.).

Project Cost Management has a total of 4 processes. Out of these 4 processes, 3 are in Planning Process Group and 1 in Monitoring and Controlling Process Group. In this post, I present, how you can easily remember the Inputs and Outputs to and from the 3 planning processes in Project Cost Management.

Step 1:
Project Cost Management Planning Processes Input and Output - Step 1

Project Cost Management Planning Processes Inputs and Outputs - Step 2

Project Cost Management Planning Processes Group Inputs and Outputs - Step 3

Monday, 4 November 2013

Memorizing Project Time Management Planning Processes - Inputs and Outputs using Cascading Inputs Method

Well, lets look at Project Time Management Planning processes. There are six planning processes here. A careful observation helps you to see that outputs of one process are used as inputs by the subsequent processes. This observation is what I call as "Cascading Inputs Method" - my own term (nothing to do with PMBoK(R) or PMI(R)). There are five steps in this method.
Step 1:
Project Time Management Planning Processes - Step 1 of Inputs and Outputs
Step 2:
Project Time Management Planning Processes - Step 2 of Inputs and Outputs
Step 3
Project Time Management Planning Processes - Step 3 of Inputs and Outputs
Step 4
Project Time Management Planning Processes - Step 4 of Inputs and Outputs
Step 5
Project Time Management Planning Processes - Step 5 of Inputs and Outputs

Project Time Management processes are very important from the PMP Exam point of view. Therefore, if you practice these steps multiple times, you can easily visualize the Inputs and Outputs. And also, certain important outputs like Project schedule network diagram, Schedule baseline, Project Schedule - which process creates them you can easily remember.

For the last process in Project Time Management i.e Control Schedule, you can see my earlier post Controlling Processes Inputs and Outputs. I have grouped Controlling processes together as there is lot of similarity between them.






Memorizing M & C Processes (excluding Integration Management Knowledge Area) Inputs and Outputs

To begin with, if I say, there are 47 inputs and 49 outputs to and from the 9 Monitoring and Controlling Processes (excluding Integration Management Knowledge Area), and you have to memorize them. You think I am mad. I might appear mad towards getting my PMP Certification, but there is a method to my madness. Read carefully below...

Do you agree that

  • The Monitoring and Controlling Processes for each Knowledge area (excluding Integration Management that is not discussed here and Human Resources Management which doesn't have a Monitoring and Controlling process) have similar purpose?
  • Each knowledge area (again  excluding Integration Management that is not discussed here and Human Resources Management which doesn't have a Monitoring and Controlling process) produces certain key project documents, other than their respective management plans, with respect to its own knowledge area? For example, Scope Management produces Requirements Management Plan, Requirements Traceability Matrix. Time Management produces Project Schedule. Quality Management produces Quality Metrics, Quality Checklists etc.
  • If you have agreed to both the questions above, then you understand that since these processes perform similar activities with respect to their own knowledge areas, there must be some common Inputs and Outputs for these processes. Isn't it?
Enough said, let us look at the I/O Diagram...

Observations on Inputs
  • Project Management Plan and Work Performance Data (WPD) is input to all the 9 Processes. Which means by remembering these two, you can remember a total of 18 inputs.
  • Organizational Process Assets (OPA) is input to Scope, Schedule, Cost and Quality Controlling Processes that start with the word "Control". To remember easily, the last three knowledge areas - Risk, Procurements and Stakeholder's Controlling processes doesn't have OPA as input. This will make you to remember another 5.
  • Requirements Management Plan and Requirements Traceability Matrix both are key Project documents that are produced by Scope Management Knowledge area, so they are input to both the Validate Scope and Control Scope processes.
  • Project Schedule, Schedule Data and Project Calenders (this comes from Procurement process as well) produced from Schedule Management Knowledge area are inputs to its respective Controlling process.
  • Like this, observe how the other key Project documents and how they go as inputs into their respective knowledge area controlling processes. For ex: Risk Register is input to Control Risks.
  • Use logic for the rest of the inputs other than common ones, and you should easily remember them.
Observations on Outputs
  • This is mind blowing... by remembering just 5 common outputs, you can actually easily remember 40 outputs of the 49. Now you should appreciate my method to madness. And remembering these common 5 outputs, you can remember 5 knowledge areas completely. 
  • Change Requests, Work Performance Information (WPI), Project Document Updates, Project Management Plan Updates and Organizational Process Assets Updates - are the five common outputs from all the processes that start with the word "Control". 
  • Both Control Schedule and Control Costs processes produce their respective Forecasts. - Important to remember for the exam.
  • Check the rest of the outputs for Control Quality and Validate Scope.
For more information
  • How the deliverable is created, validated, verified and accepted, please check my another post Deliverable Lifecycle. Its important to see this post, as Validate Scope, Control Quality both have connections with respect to Inputs and Outputs above and you can clearly visualize them in that post.
  • How Work performance data (WPD), and Work performance information (WPI) and finally Work performance reports (WPR) is related, check my another blog Work Performance data to reports process flow
  • If you observe, you will note that all the Controlling processes produce Change Requests as outputs. If you would like to know the complete Change Management flow, please follow my Change Management Process Flow
Disclaimer
  • The abbreviations WPD, WPI and WPR I have used to reduce my typing work. They are not PMI(R) abbreviations.
  • I have used this method to memorize the inputs and outputs for Controlling processes. I am sharing this information here, with the assumption that it might be beneficial for others who are preparing for PMP Exam. If you find this post or any other post, not to your understanding please feel free to post a comment, I would be glad to explain more. If you find this information is not helpful for you, please don't mind, and I am thankful for your visit anyway.



Thursday, 17 October 2013

What is created/updated when in PMBOK Processes

While preparing for the exam, another useful thing I have created is an Excel worksheet that shows for various outputs (its better to call them as Management Products as in PRICE2 and/or Project Documents) when they are created i.e. the process that creates them and updates them.

I have reproduced the list below for your information. The most important areas here to look for are:

  • When Project Management Plan is getting updated
  • When Project Documents are getting updated
  • When important Management Products like WBS, Change Requests, Milestone list etc are created
  • When Organizational Process assets and Enterprise Environmental Factors gets updates - most importantly during the Closing process
S.No Document Action Process Knowledge Area Process Group
1 Project Charter Create Develop Project Charter Integration Initiating
2 Project Management Plan Create Develop Project Management Plan Integration Planning
Update Direct and Manage Project Work Integration Executing
Update Monitor and Control Project Work Integration Monitoring and Controlling
Update Perform Integrated Change Control Integration Monitoring and Controlling
Update Control Scope Scope Monitoring and Controlling
Update Develop Schedule Schedule Planning
Update Control Schedule Schedule Monitoring and Controlling
Update Control Costs Cost Monitoring and Controlling
Update Perform Quality Assurance Quality Executing
Update Control Quality Quality Monitoring and Controlling
Update Acquire Project Team HR Executing
Update Manage Project Team HR Executing
Update Manage Communications Communications Executing
Update Control Communications Communications Monitoring and Controlling
Update Plan Risk Responses Risk Planning
Update Control Risks Risk Monitoring and Controlling
Update Conduct Procurements Procurement Executing
Update Control Procurements Procurement Monitoring and Controlling
Update Manage Stakeholder Engagement Stakeholder Executing
Update Control Stakeholder Engagement Stakeholder Monitoring and Controlling
3 Deliverables Create Direct and Manage Project Work Integration Executing
Verified Control Quality Quality Monitoring and Controlling
4 Change Requests Create Direct and Manage Project Work Integration Executing
Create Monitor and Control Project Work Integration Monitoring and Controlling
Approve Perform Integrated Change Control Integration Monitoring and Controlling
Create Validate Scope Scope Monitoring and Controlling
Create Control Scope Scope Monitoring and Controlling
Create Control Schedule Schedule Monitoring and Controlling
Create Control Costs Cost Monitoring and Controlling
Create Perform Quality Assurance Quality Executing
Validate Control Quality Quality Monitoring and Controlling
Create Control Quality Quality Monitoring and Controlling
Create Manage Project Team HR Executing
Create Control Communications Communications Monitoring and Controlling
Create Control Risks Risk Monitoring and Controlling
Create Plan Procurement Management Procurement Planning
Create Conduct Procurements Procurement Executing
Create Control Procurements Procurement Monitoring and Controlling
Create Manage Stakeholder Engagement Stakeholder Executing
Create Control Stakeholder Engagement Stakeholder Monitoring and Controlling
5 Work Performance Data Create Direct and Manage Project Work Integration Executing
6 Project Documents Create


Update Direct and Manage Project Work Integration Executing
Update Monitor and Control Project Work Integration Monitoring and Controlling
Update Perform Integrated Change Control Integration Monitoring and Controlling
Update Define Scope Scope Planning
Update Create WBS Scope Planning
Update Validate Scope Scope Monitoring and Controlling
Update Control Scope Scope Monitoring and Controlling
Update Sequence Activities Schedule Planning
Update Estimate Activity Resources Schedule Planning
Update Estimate Activity Durations Schedule Planning
Update Develop Schedule Schedule Planning
Update Control Schedule Schedule Monitoring and Controlling
Update Estimate Costs Cost Planning
Update Determine Budget Cost Planning
Update Control Costs Cost Monitoring and Controlling
Update Plan Quality Management Quality Planning
Update Perform Quality Assurance Quality Executing
Update Control Quality Quality Monitoring and Controlling
Update Manage Project Team HR Executing
Update Plan Communications Management Communications Planning
Update Manage Communications Communications Executing
Update Control Communications Communications Monitoring and Controlling
Update Perform Qualitative Risk Analysis Risk Planning
Update Perform Quantitative Risk Analysis Risk Planning
Update Plan Risk Responses Risk Planning
Update Control Risks Risk Monitoring and Controlling
Update Plan Procurement Management Procurement Planning
Update Conduct Procurements Procurement Executing
Update Control Procurements Procurement Monitoring and Controlling
Update Plan Stakeholder management Stakeholder Planning
Update Manage Stakeholder Engagement Stakeholder Executing
Update Control Stakeholder Engagement Stakeholder Monitoring and Controlling
7 Work Performance Reports Create Monitor and Control Project Work Integration Monitoring and Controlling
8 Change Log Create Perform Integrated Change Control Integration Monitoring and Controlling
9 Final Product, Service Create Close Project Integration Closing
10 Organizational Process Assets Update Close Project Integration Closing
Update Control Scope Scope Monitoring and Controlling
Update Control Schedule Schedule Monitoring and Controlling
Update Control Costs Cost Monitoring and Controlling
Update Perform Quality Assurance Quality Executing
Update Control Quality Quality Monitoring and Controlling
Update Manage Project Team HR Executing
Update Manage Communications Communications Executing
Update Control Communications Communications Monitoring and Controlling
Update Control Risks Risk Monitoring and Controlling
Update Control Procurements Procurement Monitoring and Controlling
Update Close Procurements Procurement Closing
Update Manage Stakeholder Engagement Stakeholder Executing
Update Control Stakeholder Engagement Stakeholder Monitoring and Controlling
11 Scope Management Plan Create Plan Scope Management Scope Planning
12 Requirements Management Plan Create Plan Scope Management Scope Planning
13 Requirements Documentation Create Collect Requirements Scope Planning
14 Requirements Traceability Matrix Create Collect Requirements Scope Planning
15 Project Scope Statement Create Define Scope Scope Planning
16 WBS Create Create WBS Scope Planning
17 WBS Dictionary Create Create WBS Scope Planning
18 Accepted Deliverables (Signoff) Create Validate Scope Scope Monitoring and Controlling
19 Work Performance Information Create Validate Scope Scope Monitoring and Controlling
Create Control Scope Scope Monitoring and Controlling
Create Control Schedule Schedule Monitoring and Controlling
Create Control Costs Cost Monitoring and Controlling
Create Control Quality Quality Monitoring and Controlling
Create Control Communications Communications Monitoring and Controlling
Create Control Risks Risk Monitoring and Controlling
Create Control Procurements Procurement Monitoring and Controlling
Create Control Stakeholder Engagement Stakeholder Monitoring and Controlling
20 Schedule Management Plan Create Plan Schedule Management Schedule Planning
21 Activity List Create Define Activities Schedule Planning
22 Activity Attributes Create Define Activities Schedule Planning
23 Milestone List Create Define Activities Schedule Planning
24 Project Schedule network Diagrams Create Sequence Activities Schedule Planning
25 Activity Resource requirements Create Estimate Activity Resources Schedule Planning
26 Resource breakdown structure Create Estimate Activity Resources Schedule Planning
27 Activity Duration Estimates Create Estimate Activity Durations Schedule Planning
28 Schedule Baseline Create Develop Schedule Schedule Planning
29 Project Schedule Create Develop Schedule Schedule Planning
30 Schedule Data Create Develop Schedule Schedule Planning
31 Project Calendars Create Develop Schedule Schedule Planning
32 Schedule Forecasts Create Control Schedule Schedule Monitoring and Controlling
33 Cost Management Plan Create Plan Cost Management Cost Planning
34 Activity Cost Estimates Create Estimate Costs Cost Planning
35 Basis of Estimates Create Estimate Costs Cost Planning
36 Cost Baseline Create Determine Budget Cost Planning
37 Project funding requirements Create Determine Budget Cost Planning
38 Cost forecasts Create Control Costs Cost Monitoring and Controlling
39 Quality Management Plan Create Plan Quality Management Quality Planning
40 Process Improvement Plan Create Plan Quality Management Quality Planning
41 Quality Metrics Create Plan Quality Management Quality Planning
42 Quality Checklists Create Plan Quality Management Quality Planning
43 Quality control measurements Create Control Quality Quality Monitoring and Controlling
44 Validated Changes Create Control Quality Quality Monitoring and Controlling
45 HR Management Plan Create Plan HR Management HR Planning
46 Project Staff assignments Create Acquire Project Team HR Executing
47 Resource Calendars Create Acquire Project Team HR Executing
Update Conduct Procurements Procurement Executing
48 Team Performance assessments Create Develop Project Team HR Executing
49 Enterprise environmental factors Update Develop Project Team HR Executing
Update Manage Project Team HR Executing
50 Communications Management Plan Create Plan Communications Management Communications Planning
51 Project communications Create Manage Communications Communications Executing
52 Risk Management Plan Create Plan Risk Management Risk Planning
53 Risk Register Create Identify Risk Risk Planning
54 Procurement Management Plan Create Plan Procurement Management Procurement Planning
55 Procurement SoW Create Plan Procurement Management Procurement Planning
56 Procurement Documents Create Plan Procurement Management Procurement Planning
57 Source selection criteria Create Plan Procurement Management Procurement Planning
58 Make or Buy Decisions Create Plan Procurement Management Procurement Planning
59 Selected Sellers Create Conduct Procurements Procurement Executing
60 Agreements Create Conduct Procurements Procurement Executing
61 Closed Procurements Create Close Procurements Procurement Closing
62 Stakeholder Register Create Identify Stakeholders Stakeholder Initiating
63 Stakeholder Management Plan Create Plan Stakeholder management Stakeholder Planning
64 Issue Log Create Manage Stakeholder Engagement Stakeholder Executing